Postby Noel Tudball » Wed Apr 18, 2018 10:36 am


(Click on image to view & close)

RFMilesReserve-April2018 (Medium).jpg
RFMilesReserve-April2018 (Medium).jpg (150.99 KiB) Viewed 715 times

Photo source: https://www.facebook.com/levelcrossings/photos/a.883837948357558.1073741830.843601892381164/1905080106233332/?type=3

NOTES:
  • Background to Level Crossings, Frankston Railway Line and announcements prior to 18 April 2018: http://www.seafordcc.org/forum/viewtopic.php?f=4&t=190
  • Critical dates for disruptions are listed below, by advice date
  • *** When buses replace trains, if you have special requirements such as a mobility scooter, it is recommended you call ahead to confirm your needs will be met by PTV: 1800 800 007
  • LXRA Contacts:
    o Seaford Community Hotline - 0401 697 255 or Seaford@spalliance.com.au for Seaford Rd-only community enquiries, e.g. dates, plans, construction issues, general enquiries
    o Overton Rd Community Hotline - 1800 105 105 and ask for your message to be sent to Ellen Burgin
    o 1800 105 105 24/7 Hotline - for all issues related to any crossing
Summary, Updates and Shortcuts to information

The SCC is a member of the LXRA Seaford Rd Community Reference Group (CRG) which will liaise between residents and the Level Crossing Removal Authority (LXRA).
If you have questions (and who doesn't?), please review the many questions already asked and answered here: https://your.levelcrossings.vic.gov.au/Seaford
If your question has not been answered satisfactorily, feel free to contact us and we'll liaise directly with the LXRA for you.
It is expected that many more questions will follow as the project progresses.
Other CRG members: https://levelcrossings.vic.gov.au/media/publications/seaford-community-reference-group

What is the LXRA design solution for Seaford Road? - https://your.levelcrossings.vic.gov.au/Seaford/faqs#22768
Technical reports (hydrogeology, noise, etc: https://levelcrossings.vic.gov.au/projects/seaford-road-seaford/publications
Level Crossing Removal Authority (LXRA) websites:

What is happening at other crossings? - https://www.danielbowen.com/2017/09/27/level-crossing-removals-status/

================================================================================

Recent announcements (by date):

Critical dates for disruptions:
https://levelcrossings.vic.gov.au/projects/seaford-road-seaford
http://www.metrotrains.com.au/planned-work/

4 May 2018: Seaford Road closure, buses replace trains, night works

27 April 2018: Seaford Road closure, buses replace trains, night works

20 April 2018: Very productive and informative onsite meeting on 20 April with a small handful of residents, LXRA:

20 April 2018:

23 March 2018:

7 March 2018:

6 March 2018:

5 March 2018:

1 March 2018:

28 February 2018:


Noel,
Chairman
SeafordCC@gmail.com

Facebook - click on the link in the top right-hand corner of this screen.

The Seaford Community Committee (SCC) aims to improve communication and create a stronger community in Seaford.

Image
SCC website



User avatar
Noel Tudball
Chairman
 
Posts: 657
Joined: Sun Jun 16, 2013 5:28 pm







Re: Seaford Rd Level Crossing: Construction Phase

Postby Noel Tudball » Fri Apr 20, 2018 6:58 pm


SCC Seaford Rd level crossing update: 20 April 2018

These are notes taken during a very productive and informative onsite meeting on 20 April with a small handful of residents, LXRA representative, the Alliance Community Relations Manager and the Alliance Contractor. Thank you to (resident) Jo for organising.

It is our hope that by sharing as much relevant and timely information as is practicable, we lessen some of the impact and stress on many residents who we know are extremely upset with what is happening in our lovely Seaford.

Our stated role is to aim to improve communication and create a stronger community in Seaford by representing the interests of residents and business operators in and around Seaford and we hope you find the following of interest:

  • the under rail walkway from Railway Pde to R F Miles Reserve will be located midway between Johnstone St and Weatherston Rd
  • no pedestrian lights are planned at that point - we will be advised if this changes, so that we can lobby to not have them installed due to the traffic disruption this would create, being located so close to Seaford Rd
  • the bus stop will be moved from the end of Johnstone St to the same location as the new under rail walkway - a nice bonus for anyone who has always worried about turning right into Johnstone St and getting a car in their boot - those who do will know what we're talking about - car overtakes in the bus stop - oops - power pole
  • discussions will be held with FCC and affected residents with a view to closing Weatherston Lane at the Seaford Rd end (only) to avoid people risking accidents by speeding on the wrong side of Seaford Rd to turn into Weatherston Lane in the face of oncoming traffic. The hope is to have this lane closed permanently from Seaford Rd (from the edge of the footpath/fence line)
  • electrical power along Railway Pde will be moved from the Eastern (rail) side to underground on the Western side of Railway Pde and the power poles on the Eastern side will be removed
  • since tree removal approval takes considerable time, approval for removal of all trees on the Western side of Railway Pde (the rail side) from Seaford Rd to Station St has been obtained, however:
    o (only) all of the trees on the Western side of Railway Pde (the rail side) between Seaford Rd and Johnstone St will be completely removed (starting next week)
    o North of Johnstone St along Railway Pde, only a (few) selected trees will be removed to allow access for work
  • for those wondering at the tree-trimming along Railway Pde this week, this was being carried out by United Energy (not LXRA)
  • 1 gum tree on the private property at the intersection of Railway Pde/Seaford Rd will go, possibly all - yet to be determined. This is because LXRA (road?)work near the tree is expected to interfere with the root system and balance of the tree/trees
  • the small power substation North of Johnstone St will re retained and refurbished
  • it is hoped that possum boxes will be sourced for residents wanting to accept relocated possums
  • the Alliance (contractor) can't provide soil, water, etc. reports, as the Alliance doesn't own them - we need to speak with LXRA
  • larger trucks currently using Fortescue Ave (to get to Bardia Ave) will change to using Wells Rd
  • traffic lights at the intersection of Railway Pde/Seaford Rd will always be reset back to pre work status
  • the Alliance & the contractor are also in charge of the Kananook Railway Sidings project. It is expected that it will be in the order of 6 months before designs for this area are finalised
  • a weekly onsite information session will be trialled to answer residents' questions face-to-face - details to be advised
  • it is expected that a notice of (approximate) critical dates and work items will be displayed 24/7 at the Seaford Rd crossing for residents’ information

  • LXRA Contacts:
    o Seaford Community Hotline - 0401 697 255 or Seaford@spalliance.com.au for Seaford Rd-only community enquiries, e.g. dates, plans, construction issues, general enquiries
    o Overton Rd Community Hotline - 1800 105 105 and ask for your message to be sent to Ellen Burgin
    o 1800 105 105 24/7 Hotline - for all issues related to any crossing

More information:
https://levelcrossings.vic.gov.au/projects/seaford-road-seaford

Background to Level Crossings, Frankston Railway Line and announcements prior to 18 April 2018: http://www.seafordcc.org/forum/viewtopic.php?f=4&t=190

User avatar
Noel Tudball
Chairman
 
Posts: 657
Joined: Sun Jun 16, 2013 5:28 pm



Re: Seaford Rd Level Crossing: Construction Phase

Postby Noel Tudball » Fri Apr 27, 2018 7:10 pm


27 April 2018:

More information: http://www.metrotrains.com.au/planned-work/buses-carrum-to-frankston-and-stony-point-friday-4-to-sunday-17-june/

(Click on image to view & close)

LXRA Seaford Rd May 2018-P1-night.jpg
LXRA Seaford Rd May 2018-P1-night.jpg (35.2 KiB) Viewed 459 times
LXRA Seaford Rd May 2018-P1 (Medium).jpg
LXRA Seaford Rd May 2018-P1 (Medium).jpg (73.76 KiB) Viewed 459 times
LXRA Seaford Rd May 2018-P2 (Medium).jpg
LXRA Seaford Rd May 2018-P2 (Medium).jpg (64.93 KiB) Viewed 459 times
LXRA Seaford Rd May 2018-P1.jpg
LXRA Seaford Rd May 2018-P1.jpg (193.28 KiB) Viewed 459 times
LXRA Seaford Rd May 2018-P2.jpg
LXRA Seaford Rd May 2018-P2.jpg (172.93 KiB) Viewed 459 times
User avatar
Noel Tudball
Chairman
 
Posts: 657
Joined: Sun Jun 16, 2013 5:28 pm



Re: Seaford Rd Level Crossing: Construction Phase

Postby Noel Tudball » Fri May 04, 2018 5:56 pm


4 May 2018:

(Click on image to view & close)

LXRA SeafordRd-20180504 (1) (Medium).jpg
LXRA SeafordRd-20180504 (1) (Medium).jpg (56.05 KiB) Viewed 455 times
LXRA SeafordRd-20180504 (2) (Medium).jpg
LXRA SeafordRd-20180504 (2) (Medium).jpg (46.33 KiB) Viewed 455 times
LXRASeafordRd-20180504 (2).jpg
LXRASeafordRd-20180504 (2).jpg (156.31 KiB) Viewed 522 times
LXRASeafordRd-20180504 (1).jpg
LXRASeafordRd-20180504 (1).jpg (133.61 KiB) Viewed 522 times