Seaford Rd Level Crossing Removal

PostPosted: Wed Apr 18, 2018 10:36 am
by Noel Tudball

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Fri Apr 20, 2018 6:58 pm
by Noel Tudball

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Fri Apr 27, 2018 7:10 pm
by Noel Tudball

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Fri May 04, 2018 5:56 pm
by Noel Tudball

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Sun Jun 17, 2018 6:06 pm
by Noel Tudball

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Sat Jul 07, 2018 12:23 am
by Noel Tudball

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Sat Jul 07, 2018 2:23 am
by Noel Tudball

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Sat Jul 07, 2018 2:33 am
by Noel Tudball

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Wed Jul 18, 2018 3:11 am
by Noel Tudball

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Sat Jul 28, 2018 4:56 pm
by Noel Tudball

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Sat Jul 28, 2018 5:17 pm
by Noel Tudball

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Sat Jul 28, 2018 5:48 pm
by Noel Tudball

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Sat Jul 28, 2018 6:12 pm
by Noel Tudball

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Fri Aug 03, 2018 12:51 pm
by Noel Tudball

Sign up for LXRA SMS updates about construction activities and potential impacts in Seaford & Carrum. You can opt out at any time.
Email your full name and mobile number to:

** Seaford Level Crossing Removal Project: Seaford@spalliance.com.au
** Carrum Level Crossing Removal Project: Carrum@spalliance.com.au


Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Wed Aug 08, 2018 10:25 pm
by Noel Tudball

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Sat Aug 11, 2018 1:52 am
by Noel Tudball

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Mon Aug 13, 2018 6:22 pm
by Noel Tudball

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Mon Aug 13, 2018 6:32 pm
by Noel Tudball

Re: Seaford Rd Level Crossing

PostPosted: Wed Aug 15, 2018 6:20 pm
by Noel Tudball

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Wed Aug 15, 2018 8:08 pm
by Noel Tudball

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Thu Aug 16, 2018 6:43 pm
by Noel Tudball

Sadly, as expected, advice from LXRA: more trees being removed along Railway Pde

140818 - Railway Pde_VegetationRemoval.pdf
(665.16 KiB) Downloaded 76042 times


(Click on image to view & close)
Railway Pde Trees August2018.jpg
Railway Pde Trees August2018.jpg (99.89 KiB) Viewed 2270517 times



Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Tue Sep 04, 2018 10:52 pm
by Noel Tudball

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Tue Sep 04, 2018 10:55 pm
by Noel Tudball

Seaford: Buses replace trains: Frankston and Stony Point lines
From 8:30 pm Saturday 8 September to 6:00 am Sunday 16 September 2018


For more information about train replacement bus services, visit the PTV website: https://www.ptv.vic.gov.au/live-travel-updates/

(Click on image to view & close)
xTrains-Buses (Small).jpg
xTrains-Buses (Small).jpg (42.57 KiB) Viewed 2268775 times


Works alert – Vegetation removal

PostPosted: Wed Sep 05, 2018 6:23 pm
by Noel Tudball

Works alert – Vegetation removal - MORE trees!

"As part of our work to remove the level crossing at Seaford Road the existing combined services route will need to be relocated. This will be located within the rail corridor, however, to undertake this work some trees and vegetation need to be removed."

You might like to comment here: https://www.facebook.com/SeafordCommunityCommittee/posts/2249786348386942

240818- VegetationRemoval works.pdf
(682.69 KiB) Downloaded 75561 times

Eel Race Road to Armstrongs Road

(Click on image to view & close)
240818- VegetationRemoval worksP1.jpg
240818- VegetationRemoval worksP1.jpg (154.32 KiB) Viewed 2268670 times

Armstrongs Road to McKenzie Street

(Click on image to view & close)
240818- VegetationRemoval worksP2.jpg
240818- VegetationRemoval worksP2.jpg (180.19 KiB) Viewed 2268670 times



Seaford Station: up to 70 car spaces closed

PostPosted: Wed Sep 05, 2018 11:23 pm
by Noel Tudball

"Due to construction activities near Seaford Station, up to 70 car spaces will be closed in the Railway Parade car park until mid-October 2018."

Source: https://levelcrossings.vic.gov.au/disru ... e%20closed

(Click on image to view & close)
Seaford Station car park (Medium).jpg
Seaford Station car park (Medium).jpg (73.51 KiB) Viewed 2268622 times

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Sat Sep 08, 2018 11:15 am
by Noel Tudball

Information just in from LXRA:

"Due to night works within the rail corridor, the level crossing at Station St, Seaford will be closed to traffic from 10pm on Saturday 8 September to 6am on Sunday 9 September. Traffic management will be in place."

You know the drill: detour further away.

Just in case you needed any reminding, LXRA are working 24/7 to have works finished to open the Seaford Rd/Railway Pde intersection by 28 September.


Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Fri Sep 21, 2018 5:52 pm
by Noel Tudball

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Fri Sep 21, 2018 6:38 pm
by Noel Tudball

More photos taken at Seaford, during the Seaford Road level crossing removal project.

The last image is what was promised - on many occasions - ALL of the concrete must be HIDDEN !

We have voiced our dissatisfaction at the mustard fin decorations to LXRA and our local State MP Sonya Kilkenny has promised to take our concerns further.
You can also convey your opinion to her at Sonya.Kilkenny@parliament.vic.gov.au

(Click on images to view & close)

Unfinished mustard fin "decorations" across Seaford Rd

LXRA Seaford Rd mustard fins (Mobile).jpg
Unfinished mustard fin "decorations" across Seaford Rd
LXRA Seaford Rd mustard fins (Mobile).jpg (98.15 KiB) Viewed 2266733 times
LXRA Seaford Rd mustard fins.jpg
Unfinished mustard fin "decorations" across Seaford Rd
LXRA Seaford Rd mustard fins.jpg (149.3 KiB) Viewed 2266818 times


Unfinished mustard fin "decorations" across Seaford Rd

Seaford Rd20180911_130816 (Mobile).jpg
Unfinished mustard fin "decorations" across Seaford Rd
Seaford Rd20180911_130816 (Mobile).jpg (121.48 KiB) Viewed 2266733 times
Seaford Rd20180911_130816 (2).jpg
Unfinished mustard fin "decorations" across Seaford Rd
Seaford Rd20180911_130816 (2).jpg (190.28 KiB) Viewed 2266818 times


Unfinished mustard fin "decorations" across Seaford Rd and walkway from Railway Pde to RF Miles Reserve

3RailwayPde20180911_124156 (Mobile).jpg
Unfinished mustard fin "decorations" across Seaford Rd and walkway from Railway Pde to RF Miles Reserve (central section of image removed to improve viewing on mobile devices)
3RailwayPde20180911_124156 (Mobile).jpg (99.76 KiB) Viewed 2266733 times
2RailwayPde20180911_124156 (Medium).jpg
Unfinished mustard fin "decorations" across Seaford Rd and walkway from Railway Pde to RF Miles Reserve
2RailwayPde20180911_124156 (Medium).jpg (208.97 KiB) Viewed 2266818 times


Seaford Rd Crossing Artist's impression
If we had to be content with the "hybrid bridge" that was forced upon us (rather than the trench that was requested), the very least they could have done was to hide the ugly thing. Hiding ALL the concrete was requested - and promised - on many occasions !


Seaford Rd Crossing Artist (Mobile).jpg
Seaford Rd Crossing Artist's impression
Seaford Rd Crossing Artist (Mobile).jpg (235.77 KiB) Viewed 2266733 times



Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Fri Sep 21, 2018 6:49 pm
by Noel Tudball


Link to LXRA-provided photos taken at Seaford, during the Seaford Road level crossing removal project:
https://levelcrossings.vic.gov.au/projects/seaford-road-seaford/image-gallery#gallery-326865-1

(Click on image to view & close)

UTroughs (Medium).jpg
UTroughs (Medium).jpg (152.59 KiB) Viewed 2266814 times



Railway Pde widening request

PostPosted: Mon Sep 24, 2018 3:47 pm
by Noel Tudball

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Tue Sep 25, 2018 6:08 pm
by Noel Tudball

Photos taken 25 September 2018: mobile and desktop sizes

Hiding ALL the concrete was requested - and promised - on many occasions !
The last image is what was promised - all of the concrete IS hidden !

We have voiced our dissatisfaction at the mustard fin decorations to the LXRA and our local State MP Sonya Kilkenny has promised to take our concerns further.
You can also convey your opinion to her at Sonya.Kilkenny@parliament.vic.gov.au

Someone has suggested that it's simply a ploy to make residents happy with the bridge (when it's properly finished) even though they asked for the job to be done properly - with an unobtrusive trench.

(Click on images to view & close - if the images don't load, just refresh the page)

Seaford Rd20180925 (Mobile).jpg
Seaford Rd finished decorations
Seaford Rd20180925 (Mobile).jpg (33.71 KiB) Viewed 2266253 times
Seaford Rd20180925 (Medium).jpg
Seaford Rd finished decorations
Seaford Rd20180925 (Medium).jpg (183.13 KiB) Viewed 2266253 times
Railway Pde20180925 (Mobile).jpg
Railway Pde Embankment
Railway Pde20180925 (Mobile).jpg (28 KiB) Viewed 2266253 times
Railway Pde20180925 (Medium).jpg
Railway Pde Embankment
Railway Pde20180925 (Medium).jpg (164.26 KiB) Viewed 2266253 times
Railway PdeB20180925 (Mobile).jpg
Seaford Rd/Railway Pde finished decorations
Railway PdeB20180925 (Mobile).jpg (29.06 KiB) Viewed 2266253 times
Railway PdeB20180925 (Medium).jpg
Seaford Rd/Railway Pde finished decorations
Railway PdeB20180925 (Medium).jpg (154.66 KiB) Viewed 2266253 times
Railway PdeWalkway20180925 (Mobile).jpg
Railway Pde underground walkway
Railway PdeWalkway20180925 (Mobile).jpg (31.96 KiB) Viewed 2266253 times
Railway PdeWalkway20180925 (Medium).jpg
Railway PdeWalkway20180925 (Medium).jpg (191.33 KiB) Viewed 2266253 times
Railway PdePedX'ingB20180925 (Mobile).jpg
Railway Pde pedestrian crossing
Railway PdePedX'ingB20180925 (Mobile).jpg (37.88 KiB) Viewed 2266253 times
Railway PdePedX'ingB20180925 (Medium).jpg
Railway Pde pedestrian crossing
Railway PdePedX'ingB20180925 (Medium).jpg (198.17 KiB) Viewed 2266253 times
Railway PdeC20180925 (Mobile).jpg
Railway Pde looking over RF Miles Reserve
Railway PdeC20180925 (Mobile).jpg (31.81 KiB) Viewed 2266253 times
Railway PdeC20180925 (Medium).jpg
Railway Pde looking over RF Miles Reserve
Railway PdeC20180925 (Medium).jpg (166.01 KiB) Viewed 2266253 times


Seaford Rd Crossing Artist Mobile.jpg
Seaford Rd Crossing Artist Mobile.jpg (235.77 KiB) Viewed 2266117 times



Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Wed Sep 26, 2018 5:44 pm
by Noel Tudball

A recent aerial photograph (source thanked, but withheld)

(Click on images to view & close - if the images don't load, just refresh the page)

Seaford RdSept2018 (Mobile).jpg
Seaford RdSept2018 (Mobile).jpg (29.64 KiB) Viewed 2266117 times
Seaford RdSept2018 (Medium).jpg
Seaford RdSept2018 (Medium).jpg (166.55 KiB) Viewed 2266117 times

Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Sat Oct 20, 2018 5:11 pm
by Noel Tudball

1.
Buses replacing trains - from 8.15pm to last train each night from Monday 29 October to Wednesday 31 October 2018
https://www.ptv.vic.gov.au/live-travel-updates/article/frankston-line-buses-replacing-trains-from-8-15pm-to-last-train-each-night-from-monday-29-october-to-wednesday-31-october-2018/

https://levelcrossings.vic.gov.au/disruptions/buses-replacing-trains-frankston-line

2.
DAY AND NIGHT WORKS - Friday 26 October to Sunday 28 October 2018
Armstrongs Road and Station Street, Seaford will be temporarily closed at the level crossing

Questions: 1800 105 105 or contact@levelcrossings.vic.gov.au

Download:
121018 Resident Notification - October Occupation.pdf
(575.1 KiB) Downloaded 73689 times

(Click on image to view & close)
121018 Resident Notification - October Occupation.jpg
121018 Resident Notification - October Occupation.jpg (223.2 KiB) Viewed 2261853 times




Re: Seaford Rd Level Crossing: Construction Phase

PostPosted: Fri Jan 18, 2019 1:08 am
by Noel Tudball

(Click on images to view & close)
More info: https://levelcrossings.vic.gov.au/projects/seaford-road-seaford
Questions: 1800 105 105 or contact@levelcrossings.vic.gov.au

LXRA Works alert – Seaford, Kananook, Carrum-121218-110119.jpg
LXRA Works alert – Seaford, Kananook, Carrum-121218-110119.jpg (99.83 KiB) Viewed 2245412 times

1.
LXRA 12 December 2018 Update

Works alert – Kananook Train Storage Facility
Download:

2.
DAY AND NIGHT WORKS

From 6pm Friday 18 January 2019 until 7am Monday 20 January 2019, construction activities will take place
24 hours a day along the track between Bonbeach Station and Kananook Station and across the Karrum Karrum
bridge.
Download:
LXRA Works alert – Seaford, Kananook, Carrum 110119.pdf
(157.73 KiB) Downloaded 74471 times

3.
LXRA January 2019 Update

(Click on images to view & close)
LXRAJanuary2019Update-1 (Large).jpg
LXRAJanuary2019Update-1 (Large).jpg (130.27 KiB) Viewed 2245412 times


LXRAJanuary2019Update-2 (Large).jpg
LXRAJanuary2019Update-2 (Large).jpg (129.08 KiB) Viewed 2245412 times





Re: Seaford Rd Level Crossing: Repair Phase

PostPosted: Sun Apr 07, 2019 3:12 pm
by Noel Tudball

Re: Seaford Rd Level Crossing Removal: Repair Phase

PostPosted: Mon Sep 09, 2019 5:26 pm
by Noel Tudball

September 2019: indigenous painting of some of the concrete

You may have noticed the painting underway on the four piers and walls at Seaford Road ......
Info: https://levelcrossings.vic.gov.au/media/news/a-cultural-transformation-taking-place-at-seaford-road

2019 actual:
Indigenous painting.jpg
Indigenous painting.jpg (38.83 KiB) Viewed 2217249 times


2018 Concept:
Aboriginal Cultural Design Concepts-20181015.jpg
Aboriginal Cultural Design Concepts-20181015.jpg (233.05 KiB) Viewed 2213474 times


11 September 2019: Train Tour - Carrum to Frankston

PostPosted: Mon Sep 09, 2019 5:56 pm
by Noel Tudball

Want to know more about what’s happening in Carrum and along the Frankston line?

Join members of the LXRA construction team for a train tour of the works from Carrum to Frankston:
Wednesday 11 September 2019, at 10:25am at Bonbeach Station

More: https://levelcrossings.vic.gov.au/events/train-tour-carrum-to-frankston